Nabha Power Limited V/s Punjab State Power Corporation Ltd , L&T Power Development Ltd. V/s Punjab State Electricity Regulatory

Information Type: Judicial Information
Court: Tribunals
Tribunals Name: Appellate Tribunal for Electricity
Date of Judgment(s): 2014-04-23
Case No: 207 of 2012
Case Type: Appeal
Judge Name: Rakesh Nath (Technical Member) & Surendra Kumar (Judicial Member)
Subject: Electricity Law
Statutes / Acts: Electricity Act, 2003
Section: 63
Bench Strength: Double Bench
Advocate: Sitesh Mukherjee, Aniket Prasaoon, Sakya Singha Chaudhuri et. al (P) & M G Ramachandran, Anand K. Ganesan, Swana Seshadri et. al. (R)
State of Appellant(s): Punjab
History of Case No: Challenging the order dated 1.10.2012 of Punjab State Electricity Regulatory Commission
Case Note / Description :

Appellant is entitled to claim increase in project cost due to change in scope of work of the Railway Siding due to additional works as a result of change in condition of approval by the Railway as per the provisions of the PPA under Article 13. However, the Appellant is not entitled to claim cost escalation, if any, in the works envisaged in the “In-Principle” approval of the Appeal no. 207 of 2012 Page 64 of 64 Railway which formed part of the bid documents. The Appeal is allowed in part and the impugned order is set aside to that extent. No order as to costs. The State Commission is directed to pass consequential order at the earliest preferably within 3 months of receipt of a copy of this judgment. Pronounced in the open court on this 23rd day of April, 2014. 

The Electricity Act, 2003

 
 
SignUp For News Letter

Get news and updates from OLIS group, to your email :
Contact Information
Raj Kumar (Ph.D Research Scholar)
Dr. M. Madhusudhan (Supervisor)
DEPARTMENT OF LIBRARY AND INFORMATION SCIENCE
II Floor, Tutorial Building, University of Delhi , Delhi-110 007
Mobile : +91-011-27666656
Email : info@olisindia.in
All Rights Reserved@ University of Delhi, Website Designed and Developed by Raj Kumar(Ph.D Research Scholar)